2010 Adipic Acid Facility Turnaround Schedule in Asia

2010-02-20 [Source: Pudaily]


PUdaily, Shanghai-Shandong Hongye: As its PU resin, shoe soles and polyester polyols projects will be put into operation in March, its adipic acid facility is planned to shut down for maintenance for three weeks in March;

Liaoyang Petrochemical: Adipic Acid (AA) facility is scheduled to carry out maintenance for three weeks in May;

Shandong Bohui: It has no turnaround plan for its adipic acid facility temporarily;

Xinjiang Tianli: It has no turnaround plan for its adipic acid facility temporarily;

Shenma Group: Its adipic acid facility has no maintenance plan and its 200 ktpa Nylon 66 project will be competed in the second half of 2010;

Asahi Kasei: its adipic acid (AA) in KYUSHU will carry out routine maintenance in the last ten days of April for one month.